STORY5 Introduction of Son La Hydropower Project


See drawings for location inked from Engineering Office - 2

Specifications for whole hydropower project are here

Specifications for water gates and are here

I took two (2) weeks holidays in Japan from middle of June 2008.

The first pipe (ring) was delivered to the erection site on June 19 and installed at the position for Lane 2 on next day. Installation of Lane 1 started on July 04.
Current conditions of progress of construction works at powerhouse on July 11, 2008 is as shown below.

Unit No. 1is seen at the rightest position of the above photo. Diameter of the penstock installed is about 9.6 meters. The white crawler crane of DEMAG2800 was applied to launch the penstock

Transportation of penstock was conducted as shown below.


080704-02s.JPG
Trailer

080704-03s.JPG
Penstock to be delivered with diameter of 10 meters and weight of 18 tons

080704-04s.JPG
Loading

080704-05s.JPG
Ready to go

080704-06s.JPG
Transport through public road with 7 meters wide

080704-08s.JPG
Accessing to powerhouse

080704-09s.JPG
Trailer stopped for long time on the way

080704-10s.JPG
Penstock stacked on the way. It is difficult to drive the right way, due to
lack of steering system on trailer.

080630-02s.JPG
Unit No. 2 Installed Reducer

This young engineer is Mr. "Quangspeed"who is assisting the author and
he is diligent and a hard worker.
One of starts in Vietnam
VERY GOOD!
Skilled workers of the installer, Lilama 10, have shown superior performance. But, Lilama 10 is very poor for documentation.

The pipes were installed with errors of

Unit No123456
Axial direction2mm5 mm
Perpendicular direction5mm2 mm
Elevation2mm2mm

To top Page Next page

2008-07-12 Created
2008-07-15 Revised